Phased Work
Tasks completed to date:
- Work to prepair the site was started last fall •The shower trailer, office trailer, playground and other support items were relocated • Some work was done to cofferdam the marina from the lake • The entrance was closed
- EPA burn permits have been obtained
- The project will require a huge amount of stone for both the entrance break wall and the interior of the marina itself • A stone supplier with sufficient quantities has been located
- Snake fence materials have been delivered
Upcoming tasks:
- The snake fence will be installed
- Dewatering of the marina will be commencing soon
- We will be gathering and protecting the Lake Erie Water Snakes (LEWS) with in the construction zone
- After the last LEWS is removed, earthwork will begin.
Phased work plan for
MIDDLE BASS ISLAND STATE PARK
| 2001 |
State takes acquisition of former Lonz property January |
| 2001 |
50 New docks installed |
| 2002 |
Electric hook-ups installed to 24 docks |
| 2003 |
Consultants hired to help plan development |
| 2004 |
Additional 17 acres purchased |
| 2005 |
Temporary shower and flush toilet trailer was brought to marina |
| 2006 |
20 Primitive site campground established |
| 2007 |
Permits approved by EPA, Army Corp, USFWS
- October 1, 2007 Marina closed for preparation of extensive renovation project to start spring 2008
|
| 2008 |
Marina rehabilitation, entrance channel, dock bidding and start of construction |
| 2009 |
Docks finished (tentative);
- Water/Wastewater finished (tentative)
- Buildings, sidewalks, trails, roadways and support structures underway and may be completed 2009-2010 (tentative)
|
ODNR is committed to incremental, continuous improvement of both the marina and the overall park as a solid development plan is assembled and specific construction projects are initiated. It is important to set realistic expectations for completion of first major phase of development. Construction will be influenced by the availability of capital improvement dollars, the inflated cost of constructing on the island, the short construction season due to weather and construction restrictions imposed to protect the federally endangered Lake Erie Watersnake and the fish spawning. A sense of excitement and urgency is felt as ODNR sets about the business of developing a new state park area that is based on significant and clear input through a public process and a solid, phased development plan.
|